Tal Waee CU Rehabilitation

  •  ICRC Organization and Aswar AL-Hadhaba Company
  • Tal Waee CU Rehabilitation
  • Project Value: 228,195 USD
  • Project Duration: 57 Calendar days

Excuted Work:

1- Site installation, contains of 7 tasks.
2- Mechanical works , contains of 22 tasks.
3- Civil work & Boosting station, contains 10 tasks .
4- Electrical System, contains of 12 tasks.

Main Ecxuted works:

1- Providing of materials and manpower required for rehabilitation and extension of low lift steel structure on the river.
2- Providing materials, equipment’s and man power for new complete set mechanical
crane.

Supplying of 3 Pumps

3-1 Supplying materials and providing the required equipment, labor and tools for installing and operating of 2 brand new set horizontal pump (Intermediate pumps) [ 380 VAC Y/D, 50 Hz. Q = 230 M³/hr. & H = 30 m, RPM=1450 ].
3-2 Supplying materials and providing the required equipment, labor and tools for installing and operating of brand new set horizontal pump (High lift pump) [ 380 VAC Y/D, 50 Hz. Q = 200 M³/hr. & H = 100 m, RPM=1450]
4-Supplying and installing new main electrical distribution board (2 x1.8x 0.6 depth)m & 2mm thickness, for the boosting pumps house.
5- Providing materials, equipment’s and man power for full rehabilitation of operators rooms and a Concrete Tank
6- Supply the necessary materials, equipment’s and man power for high lift crane iron frame (4×10)m beside the concrete water tank.
7- Supplying and installing new Chlorine system.
8- Install of Lamella Settlers Plates.