Rehabilitation of old badush water treatment.

  •  Oxfam Organization and Aswar AL-Hadhaba Company.
  • Project Name: Rehabilitation of old badush water treatment.
  • Project Value: 92,600 USD
  • Project Duration: 35 Calendar days

Excuted Work:

sProvide all the required skill labors, equipment and tools for erecting, installing, testing
and operating 10 pumps in Badosh WTP as following:
5. Low lift submersible pump Q=250m3/h, H=45m, power=90kw.
6. End suction high lift pump Q=100m3/h, H=150m 110kw.
7. End suction high lift pump Q=100m3/h, H=26m, power=22KW.
8. End suction high lift pump size Q=100, H=100m, power=45kw.
– fix and maintain the sedimentation tanks.
– Providing the required equipment, labor, and tools to clean the underground storage tanks.
– Providing the required equipment, to maintain the pressure filters.
– Electric works.

Related Projects

Rehabilitation of kabarly school in hamdanyiah

Rehabilitation of kabarly school in hamdanyiah

1- Rehabilitation of kabarly school in hamdanyiah / Iraq / Mosul/ Ninewa, 2- Rehabilitation of 3 schools in East of shirqat.  Contract between Save the children Organization and Aswar AL-Hadhaba Company. Project Name : 1- Rehabilitation of kabarly school in hamdanyiah...

Rehabilitation of Rubaida Bridge

Rehabilitation of Rubaida Bridge

Rehabilitation of Rubaida Bridge  A contract Between Aswar AL-Hadhaba Ltd. Company And DRC Organization Rehabilitation of Rubaida Bridge Project Value: 44,830,000 IQD Project State: Finished Project End estimation on: : 5-11-2018 Project Description: Implementation...