Rehabilitation of 304 Housing Units in Al Resala Neighborhood-Al-Jadedah Area-West Mosul
- Contract between Aswar AL-Hadhaba Ltd. Company and UNDP organization
- Rehabilitation of 304 Housing Units in Al Resala Neighborhood-Al-Jadedah Area-West Mosul
- Project Value: 865,109.00 USD
- Project State: On-going project
- Start Date: 17/06/2019
- Project End estimation on: 19 /10/2019
- Project Duration: 125 Calendar days
Project Description:
supply materials , tools , machineries and manpower to rehabilitee 304 Housing Units in Al Resala Neighborhood the works consist of all the Civil works that needed to accomplish the housing units such as [Reconstruction, Reinforced Concrete, Sandwich panal, Gypsum& cement Plastering, painting,all type of doors and windows,]And all the sanitary & electrical Works.
Related Projects
Rehabilitation of 50 Housing units in Batnaya subdistrict-Talkif District- Ninawa Governorate
Rehabilitation of 50 Housing units in Batnaya subdistrict-Talkif District- Ninawa Governorate The contract between Aswar AL-Hadhaba Ltd. Company and UNDP organization Project NameRehabilitation of 50 Housing units in Batnaya subdistrict-Talkif District- Ninawa...
Rehabilitation of 417 Housing Units in Al-Khazraj Neighborhood-West Mosul-Ninawa Governorate
Rehabilitation of 417 Housing Units in Al-Khazraj Neighborhood-West Mosul-Ninawa Governorate The contract between Aswar AL-Hadhaba Ltd. Company and UNDP organization Rehabilitation of 417 Housing Units in Al-Khazraj Neighborhood-West Mosul-Ninawa Governorate Project...
Tal Waee CU Rehabilitation
Tal Waee CU Rehabilitation ICRC Organization and Aswar AL-Hadhaba Company Tal Waee CU Rehabilitation Project Value: 228,195 USD Project Duration: 57 Calendar days Excuted Work: 1- Site installation, contains of 7 tasks. 2- Mechanical works , contains of 22 tasks. 3-...