Rehabilitation and Civil Works in Tel Afar Central Park.
- IOM Organization and Aswar AL-Hadhaba Company
- Project Name:Rehabilitation and Civil Works in Tel Afar Central Park.
- Project Value: 66,570 USD.
- Project Duration: 38 Calendar days
Excuted Work:
1- Civil works , contains of 12 Tasks.
2- Architectural Works, contains of 25 Taska.
3- MECHANICAL ( PLUMBING , Heating , Ventilation , AC – HVAC, Water, Sanitation System )
works, contains of 16 Tasks.
4- ELECTRICAL (External & Internal ), contains of 17 Tasks.
Main Ecxuted works:
1- Big Castle playset for children as following :-
Tower 4 pieces , Roof 2 pieces , double swing 1 Set, Long wave slide 1 piece,
Double slides 1 piece, Slide entry 1 piece , Spiral slide 1 piece ,Tube slide 1 piece ,
Tube passage 2 pieces , 5 step ladder 1 piece, 4 step ladder 2 pieces, Platform 4
pieces, Fugitive panel 3 pieces, Accessories 2 pieces.
2- Supplying materials and construct a fountain with a diameter of 3 meters.
3- 48 Lighting poles.
4- 40 Steel seating (chairs) with backrest.
Related Projects
Rehabilitation of kabarly school in hamdanyiah
1- Rehabilitation of kabarly school in hamdanyiah / Iraq / Mosul/ Ninewa, 2- Rehabilitation of 3 schools in East of shirqat. Contract between Save the children Organization and Aswar AL-Hadhaba Company. Project Name : 1- Rehabilitation of kabarly school in hamdanyiah...
Rehabilitation of water distribution network in (Hamdaniya) Rajim Hadid neighborhood, West Mosul
Rehabilitation of water distribution network in (Hamdaniya) Rajim Hadid neighbourhood, West MosulArea-West Mosul. ACTED Organization and Aswar AL-Hadhaba Company Rehabilitation of water distribution network in (Hamdaniya) Rajim Hadid neighbourhood, West Mosul Project...
Rehabilitation of Rubaida Bridge
Rehabilitation of Rubaida Bridge A contract Between Aswar AL-Hadhaba Ltd. Company And DRC Organization Rehabilitation of Rubaida Bridge Project Value: 44,830,000 IQD Project State: Finished Project End estimation on: : 5-11-2018 Project Description: Implementation...