Cash for Work for Painting Curbstones, Planting Trees, Removing Rubble and
Re-Arranging Loam of Main Roads

  •  The contract between Aswar AL-Hadhaba Ltd. Company and UNDP organization
  • Project Name:Cash for Work for Painting Curbstones, Planting Trees, Removing Rubble and
    Re-Arranging Loam of Main Roads (60-100) m in Al Salam Area-East Mosul.
  • Project Value: 304,725.50 USD
  • Project State: On-going project
  • Start Date: 15-7-2019
  • Project End estimation on: 15-9-2019
  • Project Duration: 45 Calendar days

Project Description:

The Project is located in East Mosul ,Al Salam Sector(Main Roads), the work to covers at 23 Km length in the sector, The works include the provision of all necessary materials, machinery, sufficient number and size of electrical generators including fuel consumption, tools, and laborers. to paint curbstones, cleaning, from the areas. removal of rubble, debris, surplus constructional materia..